SECTION 25.10. Expenditure Thresholds and Closeout Requirements


Latest version.
  • (a) Administrators must meet the expenditure threshold requirements described in paragraphs (1) - (4) of this subsection. If an Administrator fails to expend and submit expenditure documentation by the due date, the deobligation process outlined in §25.5 of this chapter (relating to Allocation, Deobligation and Termination, and Reobligation) may be initiated. A Contract may also be subject to termination for failure to meet the Contract obligations, and the Department may elect not to provide future funds to the Administrator. In such cases, the Administrator will be notified in writing of the processes described in Tex. Gov't Code, Chapter 2105 and §1.411 of this title (relating to Administration of Block Grants under Chapter 2105 of the Tex. Gov't Code). These thresholds will be proportionally reduced when the Contract Term is less than four years, although if reasonable for the proposed Activities the Department may allow a longer proportional period for the Environmental Assessment and the 30% reimbursement request.

    (1) Six-Month Threshold. An Environmental Assessment that meets the environmental clearance requirements of the Contract must be submitted to the Department within six months from the start date of the Contract;

    (2) Twenty-Month Threshold. The Administrator must have expended and submitted for reimbursement to the Department at least 30% of the total CSHC funds awarded within 20 months from the start date of the Contract;

    (3) Thirty-two-Month Threshold. The Administrator must have expended and submitted for reimbursement to the Department at least 60% of the total CSHC funds awarded within 32 months from the start date of the Contract; and

    (4) Forty-four-Month Threshold. The Administrator must have expended and submitted for reimbursement to the Department at least 90% of the total CSHC funds awarded within 44 months from the start date of the Contract.

    (b) For purposes of meeting a threshold in this section, "expended and submitted" means that a Draw request was received by the Department, is complete, and all costs needed to meet a threshold are adequately supported. The Department will not be liable for a threshold violation if a Draw request is not received by the threshold date.

    (c) The final Draw Request and complete closeout documents must be submitted no later than 60 days after the end of the Contract Term. If closeout documents are not received by this deadline, the remaining Contract balance may be subject to deobligation as the Department's liability for such costs will have expired. If an Administrator has reserved funds in the project completion report for a final Draw Request, the Administrator has 90 days after the end of the Contract Term to submit the final Draw Request, with the exception of the Department's portion of audit costs which may be reimbursed upon submission of the final Single Audit, but no later than one year after the end of the Contract Term.

Source Note: The provisions of this §25.10 adopted to be effective January 2, 2022, 46 TexReg 9009