SECTION 375.102. Alterations During Construction  


Latest version.
  • (a) Changes after approval of engineering feasibility report. The Applicant shall notify the executive administrator of any changes to the project that occur after the approval of the report but prior to the start of construction. The executive administrator shall review the proposed changes and notify the Applicant if additional engineering or other information is required. For wastewater treatment plants or other facilities required to have Commission approval, the Commission must give its approval before any substantial or material changes are made in the plans. No changes may be implemented without the express written approval of the executive administrator.

    (b) Changes during construction. Any proposed change to the construction contract must be submitted to the executive administrator in the form of a formal change order; the change order will be reviewed for compliance with program requirements. Depending upon the scope and complexity of the proposed change, approval by the executive administrator also may require amendments to other engineering and environmental documents.

Source Note: The provisions of this §375.102 adopted to be effective September 8, 2010, 35 TexReg 8126; amended to be effective July 4, 2016, 41 TexReg 4853