SECTION 371.63. Advertising and Awarding Construction Contracts  


Latest version.
  • (a) Applicable laws and rules. The Applicant shall comply with State procurement laws and rules and with applicable federal procurement rules, depending on the equivalency requirements for the financial assistance.

    (b) Executive administrator approval required. The Applicant shall not proceed to advertising for bids on the project without express written approval of the solicitation documents by the executive administrator. If the applicant proceeds to advertising without approval, it may affect eligibility for funding.

    (c) Changes prior to award. If the Applicant needs to alter the plans, specifications, or contract documents after the executive administrator's approval, then the Applicant shall:

    (1) provide the information and reasons relating to the changes therefore, if changes are required prior to bidding. The executive administrator must affirmatively approve any changes prior to advertising.

    (2) incorporate changes that occur after advertising into an addendum and provided to the executive administrator for approval as part of the bidding process.

    (d) Contract award. The text of a construction contract or a contract containing construction phase work submitted for approval prior to advertising must contain the same language and provisions as the contingently executed contract.

    (e) Pre-construction conference. The Applicant shall conduct a preconstruction conference on significant construction contracts to address the contents of the executed contract documents with the project owner, the project engineer, the prime contractor, and other appropriate parties in attendance. The Applicant shall provide the executive administrator with at least 10 days advance notice of the date, time, and location of the conference.

    (f) Notice to proceed. The executive administrator shall review the executed contract documents, including any additional documentation required by EPA for equivalency projects, and upon acceptance of same shall advise the Applicant that a notice to proceed may be issued to the contractor.

    (g) No liability. The executive administrator and the Board have no liability for any event arising out of or in any way related to project contracts or construction.

Source Note: The provisions of this §371.63 adopted to be effective June 10, 2020, 45 TexReg 3863