SECTION 321.305. General Requirements  


Latest version.
  • (a) An applicant for authorization to produce reclaimed water at a reclaimed water production facility must have:

    (1) a domestic wastewater permit for a domestic wastewater treatment facility that is located at the terminus of the collection system to which the reclaimed water production facility is or will be connected; and

    (2) an authorization to use reclaimed water under Chapter 210 of this title (relating to the Use of Reclaimed Water).

    (b) Applications for reclaimed water production facilities and for authorization to beneficially reuse reclaimed water under Chapter 210 of this title may be submitted concurrently.

    (c) The authorization of a reclaimed water production facility does not alter the permitted flow or effluent limits of the associated domestic wastewater treatment facility.

Source Note: The provisions of this §321.305 adopted to be effective November 27, 2008, 33 TexReg 9507