SECTION 74.111. Plan Review--New Equipment  


Latest version.
  • (a) A contractor must submit for review an application and plans for the installation of new equipment.

    (b) To apply for a plan review for the installation of new equipment, a contractor must:

    (1) submit a completed application on a department-approved form;

    (2) pay the fee required by §74.80; and

    (3) submit layout drawings as specified in the ASME Code A17.1 adopted in §74.100 for the specific type of equipment to be installed. These layout drawings shall also include:

    (A) the rated speed of the equipment in feet per minute;

    (B) the rated capacity of the equipment in pounds;

    (C) the total travel of the equipment in feet and inches;

    (D) elevation drawings of the hoistway, runway or wellway; and

    (E) plan drawings indicating the arrangement of the equipment in a machine room, machine space, control room or control space.

Source Note: The provisions of this §74.111 adopted to be effective July 1, 2012, 37 TexReg 4590; amended to be effective November 15, 2013, 38 TexReg 7949